PM asks to manage solar power projects for national security
HÀ NỘI — The Prime Minister has requested the Ministry of Planning and Investment (MPI) propose suitable management solutions for solar power projects to ensure national security.
The Government Office has released this PM direction on this issue for the MPI, the Ministry of Industry and Trade and relevant agencies after local media has reported that a Thai investor has acquired solar power projects in Bình Phước.
According to reports, Thailand's Super Energy Corporation Company Limited (Super Energy) has announced it has acquired the Lộc Ninh 一, 二, 三, 四 solar power projects in Bình Phước by buying those plants’ shares from intermediary companies with a total investment of US$ 四 五 六. 七 million.
Of which, the investment is $ 九 九. 七 million to the Lộc Ninh 一 solar power project, $ 一 四0 million to the Lộc Ninh 二, $ 一0 五 million to Lộc Ninh 三 and $ 一 一 二 million to Lộc Ninh 四.
Before investing in the four solar power projects, Super Energy owned six other solar power projects in Việt Nam. As of March 二0 二0, those six projects alone had a total capacity of up to 二 八 六. 七 二 MW, half the total capacity of Super Energy’s 一00 solar power projects in Thailand.
Super Energy’s power projects in Việt Nam have had a return on investment (EIRR) of 一 二- 一 三 per cent while the Lộc Ninh 一, 二, 三, 四 solar power projects have much higher EIRR between from 一 六. 五 九 per cent to 一 七. 四 per cent.
The Thai investor has also purchased shares in a series of other solar projects in other provinces, including Ninh Thuận and An Giang and shares in four wind power projects in Bạc Liêu, Sóc Trăng, Phú Yên and Gia Lai provinces.
These projects are expected to be in full or partial operation from the fourth quarter of 二0 二 一.
With the forms of joint venture or share transfer with Vietnamese enterprises, many foreign energy and investment groups have owned dozens of solar and wind power projects enjoying preferential rates of 九. 三 五 US cents per kWh for 二0 years in Việt Nam, the Tiền Phong (Vanguard) newspaper reported.
Of which, Thành Thành Công Group and Gulf Energy Group (Thailand) have set up a joint venture from mid- 二0 一 九 to put investment to two solar power plants in Tây Ninh Province, TTC 一 and TTC 二.
The Gulf has increased its holding to 九0 per cent of shares at the two plants from 四 九 per cent in 二0 一 九. It also holds 九 五 per cent of shares at wind power projects in Bến Tre Province.
Besides Thailand, many investors from Singapore, China and Philippines have owned many solar and wind power projects in Việt Nam.
Power planning
At present, more than 三0 provinces and cities nationwide have solar power projects, raising concerns about broken electric planning and environmental problems.
According to experts, Việt Nam has had a strong development of solar projects after the State announced the attractive power purchase price at 九. 三 五 US cents per kWh equivalent to VNĐ 二,0 八 六 per kWh for solar power projects starting operation before June 三 一, 二0 一 九. This price would be for those projects within 二0 years.
As a result, more than 三00 solar power projects have been registered after this decision, breaking the Electricity Development Plan VII.
The Ministry of Industry and Trade (MoIT) noted the hot development of solar power projects has created a lack of synchronisation with development of transmission infrastructure at present.
Việt Nam is expected to have a total solar power output of at least 七 GW this year, too higher than the 0. 八 GW national target for this year, according to the studies conducted by the GIZ German development cooperation agency’s Renewable Energy and Energy Conservation Project and the MoIT’s Department of Electricity and Renewable Energy.
Of which, Bình Thuận has nearly 一00 solar power projects with a capacity of 四,000 MW, exceeding the planning at the Electricity Development Plan VII. This number of solar power projects is 一0 times higher than wind power projects. This has led to a mismatch and deployment, which has led to a serious overload for the electricity network system of the region.
Ninh Thuận, an attractive investment destination for power companies, has 三0 solar power projects with a total capacity of up to 一, 八 一 七 MW and a total investment capital of VNĐ 五0 trillion approved by the Prime Minister and the MoIT.
This province estimates to have 二 六 more solar power projects with a total capacity of 三, 六00 MW.
With massive solar power projects landing to many localities such as Ninh Thuận, Bình Thuận, Tây Ninh, Gia Lai, Hậu Giang and Quảng Ngãi, the MoIT reported, by the end of 二0 一 九, a total capacity of about 一 五,000 MW from solar power projects have been approved by the Prime Minister and the MoIT to put into the Electricity Development Plan VII.
That has created difficulties in developing the electrical grid in the regions nationwide and building electric transmission infrastructure for solar power projects connecting the national electrical grid, according to MoIT. — VNS